Site
Sponsor

Commissioner Noack has road project updates for Woodlands area residents

By: Woodlands Online Staff
| Published 04/19/2022

Linkedin

THE WOODLANDS, TX – Montgomery County Precinct 3 Commissioner James Noack has announced updates to several road projects through The Woodlands area. The various projects designed to increase mobility throughout and surrounding the Township include:

“Our crews have been hard at work.”


Underground storm sewer progress on Birnham Woods Drive widening project

Contractor Main Lane Industries has been installing underground storm sewer along the northbound side of the project between Lexington Boulevard and Waterbend Cove as part of the Birnham Woods Drive widening project. The project contract was awarded in mid-January in the amount of $2,989,756.42 and is contracted for 420 calendar days.

The project will widen Birnham Woods Drive from a two-lane asphalt road to a four-lane asphalt road with roadside ditches between Waterbend Cove and Trophy Ridge. It also will widen Birnham Woods Drive from a two-lane concrete road to a four-lane concrete road with curb and gutter and underground drainage from Trophy Ridge to Rayford Road. Once completed, there will be two lanes plus a left-turn lane in each direction on Birnham Woods Drive at the intersections with Waterbend Cove and Lexington Boulevard.

Bridge work, beam placement on Gosling Road project

Contractor NBG Constructors continues to make good progress on construction of the new bridge over Spring Creek as part of the Gosling Road widening project. Some beams were placed at the beginning of April, with more scheduled for the beginning of May. The project is a joint effort, with Commissioner Noack’s office funding $4 million and Harris County Precinct 4 Commissioner Jack Cagle’s office funding the remaining $4.2 million of the $8.2 million project. The project falls within the boundaries of The Woodlands Township on both sides of the county line. The construction project started in December 2021 and is estimated to take 14-15 months to complete.

The project will widen Gosling Road to a full four-lane boulevard between Creekside Forest Drive in Harris County and Gatewood Reserve Lane on the north side of the project in Montgomery County. It will result in two 12-foot lanes in each direction. The road pavement will be 10-inch jointed reinforced concrete with 8-inch stabilized subgrade.

The widening includes the construction of a 1,817-foot bridge crossing over Spring Creek for the two new southbound lanes. The existing bridge lanes will become the two northbound lanes. The sidewalk and existing 8-foot shoulder along the northbound side will remain. The new southbound bridge will have a safety shoulder for motorists to access in case of vehicle breakdown. Northbound Gosling Road at the intersection with Creekside Forest Drive will be restriped to allow two through lanes of traffic and a left-turn lane. The additional detention will be constructed on the north side of the project and drain into Spring Creek.

Rayford Road-Birnham Woods Drive widening and signalization project

Traffic signals operating at Rayford-Birnham Woods Drive intersection – All traffic signals have been operating for about a month along Rayford Road, where four intersections were signalized as part of the Rayford Road-Birnham Woods Drive improvement project. The Rayford Road-Birnham Woods Drive traffic signals were the final ones installed.

Traffic signals replaced all-way stops at these intersections:

• Rayford Road and Birnham Woods Drive
• Rayford Road and Harmony Woods/Allegro Bend Boulevard
• Rayford Road and Spring Trails Park Drive
• Rayford Road and Harmony Creek/Harmony Forest Boulevard

Pedestrian signal poles and crosswalks have been included as part of the intersection signalization.

The project widened Rayford Road to four lanes from approximately 40 feet east of Waterbend Cove to approximately 400 feet east of Birnham Woods Drive. A new concrete roadway was constructed on the south side of the existing Rayford Road lanes to create the two new eastbound lanes. The existing road now makes up the two westbound lanes along that stretch. Left-turn lanes also were added for eastbound and westbound traffic at most intersections.
The construction included a new bridge for eastbound Rayford Road traffic just east of Spring Trails Park Drive. The project also involved widening Birnham Woods Drive to four lanes from approximately 600 feet north of Rayford Road to approximately 600 feet south of Rayford Road. All four Rayford Road-Birnham Woods Drive intersection approaches now have a dedicated left-turn lane.

Kuykendahl Road widening project

Roadside ditch grading, hydoseeding is nearing completion. Road-widening construction was completed in January for the Kuykendahl Road widening and bridge project from north of Lake Woodlands Drive to south of Bay Branch Drive. The contractor recently returned to finish ditch-grading work and hydroseed. The contractor also has been watering the newly placed hydroseed.

The project widened Kuykendahl Road from a two-lane half boulevard to a four-lane full boulevard from north of Lake Woodlands Drive to south of Bay Branch Drive. Project design included construction of two 12-foot-wide northbound vehicle lanes from north of Lake Woodlands Drive to south of Bay Branch Drive with an 8-foot-wide outside shoulder along the new northbound lanes. A new bridge was constructed over Bear Branch for the northbound lanes that has a walkway, mirroring the existing bridge. The two existing lanes are now the southbound lanes.

Repair/Rehab projects include:

• Concrete pavement repair at Sterling Ridge Drive and North Forestgate – Completed
• Concrete pavement repair at Maple Branch and Nursery Road – Upcoming
• Concrete pavement repair at Cedar Chase Place – Upcoming
• Guardrail repair at Sawdust Road and Grogan’s Mill Road – Completed
• Pressure washing Woodlands Parkway overpass at Grogan’s Mill Road – Ongoing
• Pressure washing/painting bridge rail on Grogan’s Mill Road near village shopping center - Upcoming
• Coat seal/striping of SCFL parking lot – Upcoming
• Asphalt mill/overlay Spring Ridge Drive – Upcoming

Photos
Comments •
X
Log In to Comment